Berkeley Pier-Ferry Project: Finding Aid

Every record in the Berkeley Public Records archive that bears on the proposed ferry terminal and replacement pier at the Berkeley Marina, arranged by series, with what each contains and where to read it.

Compiled November 12, 2026 from archive commit 9eca05f

Before the Council: November 17, 2026, Item 26. A public hearing to certify the project EIR, approve the project and act on its use permit. The archive holds the full packet, including the Final EIR: original (PDF, 127.6 MB, publisher's copy), searchable text. Description.

The collection

Subject
The Berkeley Water Transportation Pier-Ferry Project: a new public pier and ferry terminal at the Berkeley Marina, planned by the City of Berkeley with the San Francisco Bay Area Water Emergency Transportation Authority (WETA).
Dates
2018–2026
Extent
88 documents in 71 descriptions, plus 30 records that mention the project in passing
Creators
City of Berkeley (City Council, City Manager, Parks, Recreation & Waterfront); WETA; the Bay Conservation and Development Commission; consultants to each; members of the public
Repository
Berkeley Public Records, a public archive of City records with every file fingerprinted in a manifest. Files too large for the repository are held at the Internet Archive.
Access
Every record listed is public. Each has its original document, a plain-text version for searching, and an archive record giving its source, retrieval date and sha256.

Scope and content

The records run from the City's 2018 contract for a pier condition assessment and ferry feasibility study to the 2026 environmental impact report and the Council hearing on project approval. They include the City–WETA agreements and the contracts and grants that funded design and environmental review; WETA's business plan for Berkeley service; the parking studies; BCDC design review; and the waterfront plans and Marina Fund reports that anticipate ferry service.

A record is described here when it is about the project or carries a decision, figure or statement about it. Records that only name the project in a list are gathered under Mentions in passing. The descriptions say what each document contains. The Decision Project's analysis is on the pages listed under Analysis built on these records.

Arrangement

  1. Council actions, in order
  2. Council actions and their reports (17)
  3. Project planning and status (6)
  4. WETA records (3)
  5. Environmental review (3)
  6. Parking and transportation demand (4)
  7. Bay Conservation and Development Commission (6)
  8. Waterfront planning and the Marina Fund (14)
  9. Budget and capital program (9)
  10. Public comment and community records (4)
  11. Meeting transcripts (5)
  12. Mentions in passing
  13. Not in the archive
  14. Searching the archive yourself

Council actions, in order

Each step the City Council took on the project, with the outcome recorded in its annotated agenda.

  1. January 23, 2018 Contract No. 10632 Amendment: GHD, Inc. for Structural Condition Assessment & Ferry Transportation Feasibility Study for Berkeley Pier
    Item 17. Adopted Resolution No. 68,294–N.S.
  2. March 12, 2019 Memorandum of Understanding: Planning Phase for the viability of a potential WETA Ferry Service and Public Recreation Pier at the Berkeley Marina
    Consent Calendar Item 9. Adopted Resolution No. 68,782–N.S.
  3. June 25, 2019 Contract No. 10632 Amendment: GHD, Inc. for the WETA MOU Planning Phase
    Consent Calendar Item 30. Adopted Resolution No. 68,983–N.S.
  4. February 16, 2021 Berkeley Marina Area Specific Plan and Pier/Ferry Work Session
    Special meeting (work session) Item 2. 19 speakers. Presentation made and discussion held.
  5. December 7, 2021 Large Scale Ferry Feasibility Study – A Preferred Concept
    Special meeting (work session) Item 2. 15 speakers. Presentation made and discussion held.
  6. May 31, 2022 Berkeley Strategic Transportation Plan Update and Grant Application Opportunities
    Item 19. Adopted Resolution No. 70,399–N.S. (Water Transportation/Ferry Project), with three other resolutions.
  7. December 13, 2022 Grant Contracts with the State Coastal Conservancy to receive the FY2022 State Budget Allocation of $15 Million for improvement projects at the Berkeley Waterfront
    Special meeting Item 2. Adopted Resolution No. 70,629–N.S.
  8. July 11, 2023 Accepting grant funds from the Alameda County Transportation Commission for the Berkeley Pier Water Transportation / Ferry Project Design Phase
    Consent Calendar Item 17. Adopted Resolution No. 70,950–N.S.
  9. December 5, 2023 Nancy Skinner Municipal Pier Resolution
    Consent Calendar Item 10. Approved the recommendation (referral to the Commission).
  10. May 14, 2024 Contract: COWI North America, Inc. for Engineering and Design of the Berkeley Water Transportation Pier Ferry Project
    Consent Calendar Item 8. Adopted Resolution No. 71,326–N.S.
  11. May 14, 2024 Amendment #1 to the WETA Memorandum of Understanding for the Berkeley Water Transportation Pier Ferry Project
    Consent Calendar Item 7. Adopted Resolution No. 71,325–N.S.
  12. July 9, 2024 Contract: Rincon Consultants, Inc. for environmental support services for the Berkeley Water Transportation Pier Ferry Project
    Consent Calendar Item 11. Adopted Resolution No. 71,443–N.S.
  13. November 18, 2024 Update on the Waterfront Specific Plan for the City of Berkeley Public Tidelands Area
    Special meeting (work session) Item 1. 22 speakers. M/S/C (Taplin/Kesarwani) directing staff to complete the parking study, prepare a nature- and recreation-based concept for Cesar Chavez Park, proceed with the EIR on the highest development scenario, and return with the revised plan and EIR. Ayes 8; absent: Arreguin.
  14. September 9, 2025 Grant Agreement Amendment with State Coastal Conservancy to re-allocate $1.7M to: a) the Bay Trail Segment at Shorebird Park (design phase); and b) recreation improvements at the Gateway Pier and the J&K Parking Lot
    Consent Calendar Item 13. Adopted Resolution No. 71,943–N.S.
  15. January 27, 2026 Option Agreement with TSA Holding Group, LLC for 199 Seawall Drive
    Consent Calendar Item 6. Adopted Resolution No. 72,099–N.S.
  16. July 7, 2026 Waterfront Specific Plan Environmental Review Authorization and Near-Term Priority Adjustments
    Action Calendar Item 9. Moved to the Consent Calendar. Approved the recommendation.
  17. September 15, 2026 Grant Application: Safe Routes to Transit and Bay Trail Program (SR2TBT)
    Consent Calendar Item 12. Adopted Resolution No. 72,430–N.S.
  18. November 17, 2026 Berkeley Water Transportation Pier-Ferry Project Environmental Impact Report, Project Approval, and Use Permit
    Public Hearing Item 26. Calendared for public hearing.

Council actions and their reports

Agreements, contracts, grants and work sessions that came before the City Council, with the outcome the annotated agenda records.

January 23, 2018

Contract No. 10632 Amendment: GHD, Inc. for Structural Condition Assessment & Ferry Transportation Feasibility Study for Berkeley Pier

City of Berkeley — City Clerk · City Council, January 23, 2018, Item 17

Amends the City's contract with GHD, Inc. for a structural condition assessment and ferry transportation feasibility study for the Berkeley Pier. The archive holds the annotated agenda; the staff report is not archived.

Recorded outcome: Adopted Resolution No. 68,294–N.S.

  • Annotated Agenda — Berkeley City Council regular meeting, 2018-01-23
    City of Berkeley — City Clerk
    Original (PDF, 0.3 MB) · Text · Archive record
    berkeley-public-records:bcc-2018-01-23-regular-annotated-agenda

March 12, 2019

Memorandum of Understanding: Planning Phase for the viability of a potential WETA Ferry Service and Public Recreation Pier at the Berkeley Marina

City of Berkeley — Parks, Recreation & Waterfront (Office of the City Manager) · City Council, March 12, 2019, Consent Calendar Item 9

Memorandum of understanding with WETA for a planning phase (technical feasibility study and public engagement) on a potential ferry service and public recreation pier, accepting up to $250,000 in WETA funding.

Recorded outcome: Adopted Resolution No. 68,782–N.S.

June 25, 2019

Contract No. 10632 Amendment: GHD, Inc. for the WETA MOU Planning Phase

City of Berkeley — City Clerk · City Council, June 25, 2019, Consent Calendar Item 30

Increases the GHD, Inc. contract by $360,000, to a new amount not to exceed $690,744, for the WETA MOU planning phase (technical feasibility study and public engagement). The archive holds the annotated agenda; the staff report is not archived.

Recorded outcome: Adopted Resolution No. 68,983–N.S.

  • Annotated Agenda — Berkeley City Council regular meeting, 2019-06-25
    City of Berkeley — City Clerk
    Original (PDF, 0.3 MB) · Text · Archive record
    berkeley-public-records:bcc-2019-06-25-regular-annotated-agenda

February 16, 2021

Berkeley Marina Area Specific Plan and Pier/Ferry Work Session

City Council, February 16, 2021, Special meeting (work session) Item 2

Council work session on the Marina Area Specific Plan and the Berkeley Pier/Ferry Facility Planning Study: agenda material and the staff presentation on the status of both projects, waterfront issues and possible solutions.

Recorded outcome: 19 speakers. Presentation made and discussion held.

  • Berkeley Marina Area Specific Plan and Pier/Ferry Work Session
    City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront
    Original (PDF, 7.8 MB) · Archive record
    berkeley-public-records:waterfront-2021-02-16-berkeley-marina-area-specific-plan-and-pier-ferry-work-session
  • Berkeley Marina Area Specific Plan + Berkeley Pier/Ferry Facility Planning Study (Council Worksession presentation)
    City of Berkeley — Parks, Recreation & Waterfront
    Original (PDF, 11.0 MB) · Text · Archive record
    berkeley-public-records:waterfront-2021-02-16-berkeley-marina-area-specific-plan-berkeley-pier-ferry-facility
  • Annotated agenda, February 16, 2021
    Original (PDF, 58 KB) · Text · Archive record
    berkeley-public-records:bcc-2021-02-16-special-annotated-agenda

May 31, 2022

Berkeley Strategic Transportation Plan Update and Grant Application Opportunities

City of Berkeley — City Clerk · City Council, May 31, 2022, Item 19

Transportation plan update and grant applications. The annotated agenda records a separate resolution for the Water Transportation/Ferry Project among the item's four resolutions; the staff report is not archived.

Recorded outcome: Adopted Resolution No. 70,399–N.S. (Water Transportation/Ferry Project), with three other resolutions.

  • Annotated Agenda — Berkeley City Council regular meeting, 2022-05-31
    City of Berkeley — City Clerk
    Original (PDF, 0.3 MB) · Text · Archive record
    berkeley-public-records:bcc-2022-05-31-regular-annotated-agenda

December 13, 2022

Grant Contracts with the State Coastal Conservancy to receive the FY2022 State Budget Allocation of $15 Million for improvement projects at the Berkeley Waterfront

City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront · City Council, December 13, 2022, Special meeting Item 2

Grant contracts for a $15 million state allocation to five waterfront projects, including $2.961 million for environmental review and design of the Pier-Ferry Project.

Recorded outcome: Adopted Resolution No. 70,629–N.S.

July 11, 2023

Accepting grant funds from the Alameda County Transportation Commission for the Berkeley Pier Water Transportation / Ferry Project Design Phase

City of Berkeley — Parks, Recreation & Waterfront (Office of the City Manager) · City Council, July 11, 2023, Consent Calendar Item 17

Accepts an Alameda County Transportation Commission grant of $5,138,685 for the design phase of the Berkeley Pier Water Transportation/Ferry Project.

Recorded outcome: Adopted Resolution No. 70,950–N.S.

December 5, 2023

Nancy Skinner Municipal Pier Resolution

City of Berkeley — City Council (Councilmember Taplin, author; Kesarwani, co-sponsor) · City Council, December 5, 2023, Consent Calendar Item 10

Councilmember item, authored by Taplin and co-sponsored by Kesarwani, referring to the Parks, Recreation and Waterfront Commission a resolution to rename the Berkeley Municipal Pier for State Senator Nancy Skinner.

Recorded outcome: Approved the recommendation (referral to the Commission).

May 14, 2024

Contract: COWI North America, Inc. for Engineering and Design of the Berkeley Water Transportation Pier Ferry Project

City of Berkeley — Parks, Recreation & Waterfront (Office of the City Manager) · City Council, May 14, 2024, Consent Calendar Item 8

Engineering and design contract with COWI North America, Inc., not to exceed $6,500,000.

Recorded outcome: Adopted Resolution No. 71,326–N.S.

May 14, 2024

Amendment #1 to the WETA Memorandum of Understanding for the Berkeley Water Transportation Pier Ferry Project

City of Berkeley — Parks, Recreation & Waterfront (Office of the City Manager) · City Council, May 14, 2024, Consent Calendar Item 7

Amendment #1 to the City–WETA memorandum of understanding, accepting up to $3,000,000 in WETA funding for the engineering, design and environmental phase.

Recorded outcome: Adopted Resolution No. 71,325–N.S.

July 9, 2024

Contract: Rincon Consultants, Inc. for environmental support services for the Berkeley Water Transportation Pier Ferry Project

City of Berkeley — Parks, Recreation & Waterfront (Office of the City Manager) · City Council, July 9, 2024, Consent Calendar Item 11

Environmental support services contract with Rincon Consultants, Inc., not to exceed $3,080,000 including $280,000 of contingency, for July 15, 2024 through June 1, 2027.

Recorded outcome: Adopted Resolution No. 71,443–N.S.

November 18, 2024

Update on the Waterfront Specific Plan for the City of Berkeley Public Tidelands Area

City Council, November 18, 2024, Special meeting (work session) Item 1

Waterfront Specific Plan update, with a section on the Berkeley Pier with Ferry Access Project and on the waterfront parking and transportation demand management study, which the project funded.

Recorded outcome: 22 speakers. M/S/C (Taplin/Kesarwani) directing staff to complete the parking study, prepare a nature- and recreation-based concept for Cesar Chavez Park, proceed with the EIR on the highest development scenario, and return with the revised plan and EIR. Ayes 8; absent: Arreguin.

  • Update on the Waterfront Specific Plan for the City of Berkeley Public Tidelands Area
    City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront
    Original (PDF, 7.3 MB) · Text · Archive record
    berkeley-public-records:bcc-2024-11-18-special-item-01-staff-report
  • Waterfront Specific Plan for the City of Berkeley Public Tidelands Area (Council Worksession presentation)
    City of Berkeley — Parks, Recreation & Waterfront
    Original (PDF, 8.5 MB) · Text · Archive record
    berkeley-public-records:bcc-2024-11-18-special-item-01-presentation
  • Annotated agenda, November 18, 2024
    Original (PDF, 0.1 MB) · Text · Archive record
    berkeley-public-records:bcc-2024-11-18-special-annotated-agenda

September 9, 2025

Grant Agreement Amendment with State Coastal Conservancy to re-allocate $1.7M to: a) the Bay Trail Segment at Shorebird Park (design phase); and b) recreation improvements at the Gateway Pier and the J&K Parking Lot

City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront · City Council, September 9, 2025, Consent Calendar Item 13

Reallocates $1.7 million within the State Coastal Conservancy grant and reports the status of the funded projects, including environmental review and design of the Pier-Ferry Project (completion in 2027).

Recorded outcome: Adopted Resolution No. 71,943–N.S.

January 27, 2026

Option Agreement with TSA Holding Group, LLC for 199 Seawall Drive

City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront · City Council, January 27, 2026, Consent Calendar Item 6

Option agreement for the 199 Seawall Drive building; states that design and environmental permitting for related site improvements are under way, at 30% design, as part of the Pier Ferry project.

Recorded outcome: Adopted Resolution No. 72,099–N.S.

July 7, 2026

Waterfront Specific Plan Environmental Review Authorization and Near-Term Priority Adjustments

City of Berkeley — Councilmember Terry Taplin, District 2 · City Council, July 7, 2026, Action Calendar Item 9

Councilmember item (Taplin) authorizing environmental review of the Waterfront Specific Plan. It reports the completed Pier-Ferry parking and TDM plan and its designation of the Seawall Drive Lot (250 spaces) as the primary ferry parking.

Recorded outcome: Moved to the Consent Calendar. Approved the recommendation.

September 15, 2026

Grant Application: Safe Routes to Transit and Bay Trail Program (SR2TBT)

City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront · City Council, September 15, 2026, Consent Calendar Item 12

Authorizes an application to the Metropolitan Transportation Commission for up to $25,000,000 toward construction of landside elements of the Pier-Ferry Project. The program requires no local match.

Recorded outcome: Adopted Resolution No. 72,430–N.S.

November 17, 2026

Berkeley Water Transportation Pier-Ferry Project Environmental Impact Report, Project Approval, and Use Permit

City of Berkeley — Office of the City Manager · City Council, November 17, 2026, Public Hearing Item 26

Staff report and full packet for the public hearing to certify the project EIR (SCH #2025040995), adopt CEQA findings and a mitigation monitoring and reporting program, approve the project, and act on its use permit. The packet includes the Final EIR.

Recorded outcome: Calendared for public hearing.

Project planning and status

Feasibility work, public engagement, project updates and City plans that describe the project.

October 21, 2021

Berkeley Pier/Ferry Feasibility Study — Online Questionnaire #1 Results Report

City of Berkeley Department of Parks, Recreation and Waterfront and San Francisco Bay Area Water Emergency Transportation Authority (WETA)

Results report for the first online questionnaire of the Berkeley Pier/Ferry Feasibility Study, issued by the City and WETA.

December 7, 2021

Large Scale Ferry Feasibility Study – A Preferred Concept

City of Berkeley — Parks, Recreation and Waterfront (Office of the City Manager) · City Council, December 7, 2021, Special meeting (work session) Item 2

Agenda material for the December 7, 2021 Council work session on the Large Scale Ferry Feasibility Study: the preferred concept's waterside and landside elements and its capital cost estimate.

Recorded outcome: 15 speakers. Presentation made and discussion held.

December 7, 2021

Large Scale Ferry Feasibility Study (City Council Work Session presentation)

City of Berkeley — Parks, Recreation & Waterfront · Worksession Item 02

Slides from the December 7, 2021 work session, presented by City, WETA and consultant staff: the City–WETA partnership, public engagement, the preferred concept, and the WETA business plan.

March 18, 2025

City of Berkeley 2024 Local Hazard Mitigation Plan, Final

City of Berkeley

Citywide hazard plan; notes the two small-scale commuter ferries operating from the Marina and names added ferry and bus service as a substitute for BART after a major Hayward fault earthquake.

April 15, 2025

Climate Action Plan and Resilience Update

City of Berkeley — Office of the City Manager · Information Calendar Item 23

Information report; describes the project as reconstruction of the Berkeley Pier with all-electric ferry service between Berkeley and San Francisco.

October 24, 2025

Berkeley Pier-Ferry Project Update (City Manager off-agenda memo)

City of Berkeley — Office of the City Manager

City Manager off-agenda memo on the project's status: design, environmental review, cost estimate, funding, and answers to frequently asked questions.

WETA records

Records of the San Francisco Bay Area Water Emergency Transportation Authority, the ferry operator and the City's partner.

March 17, 2022

WETA Berkeley Ferry Service Business Plan, Version 1.0

San Francisco Bay Area Water Emergency Transportation Authority (WETA); prepared by Economic & Planning Systems for CDM Smith

WETA's business plan for Berkeley ferry service, prepared by Economic & Planning Systems for CDM Smith: ridership, vessels, operating costs, fares, farebox recovery, and capital and operating funding sources.

October 10, 2024

Richmond Service Update

San Francisco Bay Area Water Emergency Transportation Authority (San Francisco Bay Ferry)

WETA board presentation on Richmond service and the five-year operating plan; lists Berkeley–San Francisco service for FY29 in Tier 1 of WETA's 2050 Service Vision.

August 14, 2025

2025 Onboard Ferry Survey Summary Report

San Francisco Bay Area Water Emergency Transportation Authority (WETA); prepared and conducted by Corey, Canapary & Galanis Research

Summary report of WETA's 2025 onboard rider survey, conducted by Corey, Canapary & Galanis Research.

Environmental review

CEQA documents. The Final EIR is in the archive inside the November 17, 2026 Council packet (Council actions, above).

May 19, 2025

Paul Kamen, Naval Architect P.E. — Addendum to Pier-Ferry EIR scoping comments (email to City staff with attachment)

Paul Kamen (private commenter); published by the City of Berkeley in the Pier-Ferry project document library

Addendum to EIR scoping comments from Paul Kamen, naval architect, on parking demand, vessel electrification and emergency use; published in the City's project document library.

February 28, 2026

Berkeley Water Transportation Pier Ferry Project Draft Environmental Impact Report

City of Berkeley — Parks, Recreation & Waterfront Department (prepared by Rincon Consultants, Inc.)

Draft EIR prepared by Rincon Consultants: project description, impact analysis, mitigation, alternatives, and a summary of scoping comments.

June 30, 2026

Draft EIR Appendices (1 of 2 and 2 of 2)

Technical appendices to the Draft EIR, in two volumes.

  • Berkley Water Transportation Pier Ferry Project Draft EIR Appendices (1 of 2)
    City of Berkeley — Parks, Recreation, & Waterfront Department
    Original (PDF, 62.2 MB, Internet Archive) · Text · Archive record
    berkeley-public-records:pier-ferry-2026-06-30-draft-eir-appendices-1-of-2
  • Berkley Water Transportation Pier Ferry Project Draft EIR Appendices (2 of 2)
    City of Berkeley — Parks, Recreation, & Waterfront Department
    Original (PDF, 9.8 MB) · Text · Archive record
    berkeley-public-records:pier-ferry-2026-06-30-berkley-water-transportation-pier-ferry-project-draft-eir-appendices

Parking and transportation demand

Parking studies and plans for ferry riders and other waterfront users.

March 7, 2025

Water Transportation Pier-Ferry Project Parking and TDM Plan, Public Draft

City of Berkeley — Parks, Recreation & Waterfront (prepared by Kittelson & Associates, Inc.)

Parking and transportation demand management plan by Kittelson & Associates: existing waterfront parking, demand added by ferry service and other new uses, and TDM and parking strategies.

May 7, 2025

Water Transportation Pier-Ferry Project Parking and TDM Plan, Revised Draft Addendum

City of Berkeley — Parks, Recreation & Waterfront (prepared by Kittelson & Associates, Inc.)

Revised draft addendum to the March 2025 parking and TDM plan.

May 8, 2026

Berkeley Water Transportation Ferry Pier Project: Draft Parking Management Implementation Plan, Public Review Draft

City of Berkeley — Parks, Recreation & Waterfront

Public review draft of the project's parking management implementation plan.

September 9, 2026

Parks, Recreation, and Waterfront Commission Regular Meeting Agenda, September 9, 2026

City of Berkeley — Parks, Recreation & Waterfront · Item 9

Commission agenda packet. Its attached draft minutes record a Commission discussion of the Draft Pier-Ferry Parking Management Implementation Plan, and the agenda lists the Pier-Ferry Project as a future item.

Bay Conservation and Development Commission

BCDC design review, permitting, and the Bay Plan that governs it.

May 12, 2025

Public comments received for the May 12, 2025 BCDC Design Review Board meeting (Berkeley Waterfront and Berkeley Pier Ferry Project)

San Francisco Bay Conservation and Development Commission (BCDC), State of California

Public comments BCDC received for that briefing.

May 12, 2025

Berkeley Waterfront and Berkeley Pier Ferry Project; Pre-Application Briefing (For Design Review Board consideration on May 12, 2025)

San Francisco Bay Conservation and Development Commission (BCDC), State of California

BCDC staff report for the Design Review Board's pre-application briefing on the project, May 12, 2025.

February 25, 2026

Draft Summary of November 3, 2025, BCDC Design Review Board Meeting (Berkeley Waterfront and Ferry Pier)

San Francisco Bay Conservation and Development Commission (BCDC), State of California

Draft summary of the BCDC Design Review Board's November 3, 2025 review of the Berkeley Waterfront and Ferry Pier, with attached public comment.

July 31, 2026

San Francisco Bay Plan

San Francisco Bay Conservation and Development Commission

BCDC's San Francisco Bay Plan, the basis for its permit decisions; its transportation findings and policies refer to ferry service and terminals.

August 6, 2026

Listing of Administrative Matters (For Commission consideration on August 6, 2026)

San Francisco Bay Conservation and Development Commission

BCDC listing that includes the City's application for a paid parking program at three waterfront lots; it notes that the City and WETA propose the Pier Ferry Project, for which a major permit application is anticipated.

August 6, 2026

Approved Minutes of August 6, 2026 Hybrid Commission Meeting

San Francisco Bay Conservation and Development Commission

Approved BCDC minutes; public comment on the waterfront paid parking application connects it to parking for the ferry project.

Waterfront planning and the Marina Fund

Specific plans, consultant studies and Marina Fund reports that treat the ferry as part of the waterfront's future.

April 12, 2018

Waterfront / Marina Fund Update

City of Berkeley — Office of the City Manager

Report on the Marina Fund; names redevelopment of the Berkeley Pier to include a WETA ferry terminal among planned waterfront projects.

October 10, 2018

Request for Proposals (RFP), Specification No. 18-11248-C, for the Berkeley Marina Area Specific Plan (BMASP) & Draft Environmental Impact Report (DEIR)

City of Berkeley — Finance Department, General Services Division

Request for proposals for the Marina Area Specific Plan; lists the pier structural assessment and the small-scale and WETA ferry terminal feasibility studies as ongoing.

February 14, 2020

Berkeley Marina Loan Feasibility Report

California Department of Parks and Recreation, Division of Boating and Waterways

State Division of Boating and Waterways loan feasibility report; records the City's expectation that new revenue such as ferry service would offset Marina capital costs from FY 2025/26.

March 26, 2021

Berkeley Marina Area Specific Plan: Draft Existing Amenities and Operations Assessment

City of Berkeley — Parks, Recreation & Waterfront (written by Keyser Marston Associates, Inc.)

Keyser Marston assessment of Marina amenities and operations; treats large-scale ferry service as a development opportunity and a condition of its upper-end food and beverage estimate.

April 19, 2021

Berkeley Marina Area Specific Plan: Draft Implementation Strategy

City of Berkeley — Parks, Recreation & Waterfront (written by Keyser Marston Associates, Inc.)

Keyser Marston implementation strategy; estimates the revenue potential of large-scale ferry service to the Marina Fund.

February 16, 2022

Berkeley Waterfront CIP Projects 2008 to Present

City of Berkeley — Office of the City Manager

List of waterfront capital projects since 2008 with amounts and funding sources, including the completed Pier-Ferry Feasibility Study.

June 8, 2022

Berkeley Marina Area Specific Plan Update

City of Berkeley — Office of the City Manager

Specific plan status memo with a timeline of meetings, including the February 16, 2021 BMASP and Pier/Ferry work session.

August 31, 2022

AB 691 Summary - Berkeley

California State Lands Commission

State Lands Commission summary of Berkeley's sea-level-rise assessment for its granted tidelands; mentions a potential partnership with WETA on a ferry terminal.

September 22, 2022

Revised Draft Assessment: Revenue Generating Potential and Financial Feasibility of New Hotel and Food and Beverage Development Within the Berkeley Marina Area

City of Berkeley — Parks, Recreation & Waterfront (prepared by Keyser Marston Associates, Inc., as a subconsultant to Hargreaves Jones)

Keyser Marston hotel and food and beverage feasibility assessment; conditions its upper-end estimate on complementary uses including large-scale ferry service.

March 20, 2023

Update on the Waterfront Specific Plan (Council work session, March 20, 2023)

Work session report and presentation; states that the Pier/Ferry project would proceed separately, with its own project-level CEQA review, and be included as a use in the specific plan.

  • Update on the Waterfront Specific Plan for the City of Berkeley Public Tidelands Area
    City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront
    Original (PDF, 3.7 MB) · Text · Archive record
    berkeley-public-records:bcc-2023-03-20-ws-item-01-staff-report
  • Waterfront Specific Plan for the City of Berkeley Public Tidelands Area (City Council worksession presentation)
    City of Berkeley — Parks, Recreation & Waterfront
    Original (PDF, 26.8 MB, Internet Archive) · Text · Archive record
    berkeley-public-records:waterfront-2023-03-20-waterfront-specific-plan-for-the-city-of-berkeley-public-tidelands

September 23, 2023

DRAFT Waterfront Specific Plan for the City of Berkeley Public Tidelands Area (Public Draft September 23, 2023)

City of Berkeley — Parks, Recreation & Waterfront

First public draft of the Waterfront Specific Plan; discusses the pier and ferry project.

January 23, 2024

Waterfront Specific Plan Update

City of Berkeley — Office of the City Manager

Memo postponing the specific plan's Council meeting until the Pier Ferry project's parking and TDM study is complete, and describing the study's funding.

November 8, 2024

DRAFT Waterfront Specific Plan for the City of Berkeley Public Tidelands Area (Public Draft November 8, 2024)

City of Berkeley — Parks, Recreation & Waterfront

Second public draft of the Waterfront Specific Plan; lists a reopened Berkeley Pier and ferry access among the amenities it plans for.

October 28, 2025

Marina Fund Update (presentation)

City of Berkeley — Parks, Recreation & Waterfront · Item 3

Marina Fund presentation; lists Berkeley Pier/Ferry ($11.1M) among grant-funded waterfront projects.

Budget and capital program

Capital plans, bond reports and budget documents that carry the project.

January 21, 2020

Update on Measure T1 City Infrastructure Bond Program

City of Berkeley — Office of the City Manager; Parks, Recreation & Waterfront; Public Works · Information Calendar Item 52

Measure T1 status report; records that the pier planning phase was expanded to study a potential ferry facility and public recreation on a shared pier.

December 15, 2020

Revised Agenda Packet, Berkeley City Council meeting of December 15, 2020 (contains Item 14, Measure T1 Phase 2, at packet pp. 203-243)

City of Berkeley — City Clerk (agenda packet) · Item 14

Measure T1 Phase 2 project selection; records support for rebuilding the pier and willingness to consider sharing it with a WETA ferry facility, and states that reconstruction by Berkeley acting alone is beyond T1 funding.

March 16, 2021

Parks Capital Improvement Plan, Recent Projects and Ongoing Needs

City of Berkeley — Office of the City Manager · Worksession Item 3a

Parks capital work session report; lists the Municipal Pier Structural Assessment and Ferry Feasibility Study with its funding sources (T1, Marina Fund, WETA).

July 17, 2024

Reference Information for Potential Parks Tax Increase

City of Berkeley — City Manager's Office

Background for a parks tax measure; its table of unfunded waterfront needs includes the Berkeley Pier with Ferry Access Project and the grant and WETA funding received.

March 28, 2025

Parks, Recreation, and Waterfront Department Capital Improvement Project and Minor Maintenance Program Update

City of Berkeley — Office of the City Manager

Department capital update; lists the Berkeley Pier – Water Transportation Project in design, funded by grants and WETA, and the unfunded waterfront needs.

November 6, 2025

First Amendment to the FY 2026 Annual Appropriations Ordinance (AAO#1) and Preliminary FY 2025 Year-end Status (presentation)

City of Berkeley — Finance/Budget Office, Budget & Finance Policy Committee · Budget & Finance Policy Committee Item 02a

Budget amendment presentation; lists $964,158 for Berkeley Pier w/Ferry Access among other funds.

May 28, 2026

Proposed Five-Year Capital Improvement Program, Fiscal Years 2027-2031 (presentation)

City of Berkeley · Item 2

Proposed CIP presentation; lists the ACTC and WETA grants to the Berkeley Pier–Water Transportation Project and the design and environmental phase.

June 16, 2026

Proposed Five-Year Capital Improvement Program (CIP) and Proposed Five-Year CIP Public Hearing No. 1

City of Berkeley — Office of the City Manager; Budget Office · Item 40c

Proposed FY 2027–2031 CIP; lists the Pier Ferry Project's design and environmental phase and its grant funding.

June 23, 2026

Adoption of Fiscal Years 2027 and 2028 Biennial Budget and Fiscal Years 2027 – 2031 Capital Improvement Program

City of Berkeley — Office of the City Manager; Budget Office · Special Meeting Item 01

Budget adoption report; carries the same CIP listing of the Pier Ferry Project's design and environmental phase.

Public comment and community records

Commission minutes, communications listings and published third-party material.

June 29, 2021

Communications to the Council on the ferry, as listed in annotated agendas

Each annotated agenda lists the written communications the Council received, by subject and sender. These meetings list communications on the ferry, the pier or the waterfront parking plan. The communications themselves are not in the public archive.

November 12, 2025

Parks, Recreation, and Waterfront Commission — Regular Meeting, Wednesday, November 12, 2025 — Minutes - Draft (with attachments)

City of Berkeley — Parks, Recreation and Waterfront Commission · Item 17

Commission minutes; public comment includes ferry options.

March 11, 2026

Parks, Recreation, and Waterfront Commission — Regular Meeting, Wednesday, March 11, 2026 — Minutes - Draft (with attachments)

City of Berkeley — Parks, Recreation and Waterfront Commission · Item 9 and Item 12

Commission minutes; public comment on the Draft EIR, the ferry and the Marina parking plan.

October 1, 2026

The State of Recreational Access to The San Francisco Bay: 2026, Annual Site Access Audit (San Francisco Boardsailing Association)

San Francisco Boardsailing Association (SFBA), a nonprofit windsurfing and water-sports user group

Annual site audit by the San Francisco Boardsailing Association, a water-sports user group; its Berkeley Marina entry addresses paid parking and the proposed ferry terminal. Published third-party document.

Meeting transcripts

Machine caption transcripts of meetings where the project came up. The archive's transcripts begin in December 2024; earlier meetings have annotated agendas only.

June 24, 2025

BCC 2025-06-24 Special Captioning

Public comment connects proposed Marina parking charges to future ferry riders.

April 16, 2026

BCC 2026-04-16 Budget Committee Captioning

Public comment raises the cost of the new ferry and pier.

  • Text · Archive record
    berkeley-public-records:bcc-2026-04-16-budget-committee-captions-text

July 7, 2026

BCC 2026-07-07 Regular Captioning

The meeting at which Item 9 (Waterfront Specific Plan environmental review) was moved to the Consent Calendar and approved.

September 15, 2026

BCC 2026-09-15 Regular Captioning

Public comment on Item 12, the SR2TBT grant application for the project's landside elements.

October 22, 2026

2026-10-22 Budget Committee Captioning Text- Policy Committee

City of Berkeley — City Clerk

Waterfront discussion that refers to State Coastal Conservancy funding for a parking lot and the adjacent old ferry dock; public comment addresses the ferry.

Mentions in passing

These records name the project, the pier or WETA without describing them: a line in a project list, a definition, a planning narrative, a cross-reference. Annotated agendas for 2025-05-20, 2025-06-17 (both versions), 2025-06-24 and 2026-06-23 match 'ferry' only because a speaker's surname is Ferry.

Not in the archive

Searching the archive yourself

The archive adds records daily, and this aid lists what it held at commit 9eca05f. To find what has arrived since, use two searches.

The project collection. The archive files the project's records under the collection pier_ferry, in L0/sources/pier_ferry (originals) and L1/sources/pier_ferry (text).

Everything else. Council reports, agendas, transcripts and other agencies' records that discuss the ferry are filed by document type, so they turn up only by searching the text. GitHub code search covers most of it. For a complete search, clone the archive and search its text layers:

git clone --depth 1 https://github.com/ericdf/berkeley-public-records
cd berkeley-public-records
grep -rliE 'ferr(y|ies)|WETA' L1 L2 T0

Expect false positives, such as the speaker surnamed Ferry. Cite a record by its archive id and check the copy you read against the sha256 in its archive record.